Question 1
Video of a press changeover shows the operator stopping the press, then locating and presetting the next die before removing the installed die. Engineering confirms that locating and presetting can be completed at a separate station while the current batch runs; die removal still requires the approved shutdown procedure. A SMED improvement should change the sequence by:
Show answer & explanation
Correct answer: A - Locating and presetting the next die before stopping the press.